Which practice coordinates dependencies weekly?

Boost your SAFe Scaled Agile skills with our comprehensive exam preparation quiz. Tackle multiple choice questions, review hints, and understand detailed explanations to ace your SAFe certification confidently!

Multiple Choice

Which practice coordinates dependencies weekly?

Explanation:
Coordinating dependencies across multiple teams on a regular cadence is handled by the Scrum of Scrums. In this practice, a representative from each Agile Team (often the Scrum Master) meets to surface cross‑team dependencies, blockers, and integration risks. The weekly rhythm keeps teams aligned, helps resolve issues before they derail multiple teams, and supports the ART’s ongoing synchronization as work is delivered across teams. This differs from PI Planning, which is a large, endpoints-in-time planning event for the next Program Increment; System Demo, which showcases integrated progress at intervals; and Release Planning, which focuses on coordinating a set of features for a broader release horizon rather than ongoing cross‑team dependency coordination.

Coordinating dependencies across multiple teams on a regular cadence is handled by the Scrum of Scrums. In this practice, a representative from each Agile Team (often the Scrum Master) meets to surface cross‑team dependencies, blockers, and integration risks. The weekly rhythm keeps teams aligned, helps resolve issues before they derail multiple teams, and supports the ART’s ongoing synchronization as work is delivered across teams. This differs from PI Planning, which is a large, endpoints-in-time planning event for the next Program Increment; System Demo, which showcases integrated progress at intervals; and Release Planning, which focuses on coordinating a set of features for a broader release horizon rather than ongoing cross‑team dependency coordination.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy